Review times
Prince George's County building permit review times
Typical first-review times. Actual times depend on the office's queue and on how complete the first submission is.
- Commercial Building Permit with U&O (first review cycle)4–6 weeks
- Residential Addition / Alteration3–8 weeks
- New Commercial Construction8–16 weeks
- Fire Sprinkler / Fire Alarm~1 week
- MEP (Mechanical / Electrical / Plumbing)2–5 weeks