Review times
Commercial Permit review times by jurisdiction
Typical first review for new commercial construction, from each office's published figures. Where an office publishes no figure for that, its closest path is shown and named. Fairfax County, Arlington, Montgomery County and Washington, D.C. figures last verified August 10, 2026. Fewer comment rounds is the part you control.
- Fairfax County10–16 weeks
- Arlington (High-Rise Commercial Construction)8–14 weeks
- Montgomery County10–20 weeks
- Loudoun County8–16 weeks
- Prince William County8–16 weeks
- Stafford County8–14 weeks
- Howard County8–16 weeks
- Frederick County (New Commercial under 5,000 sq ft)~2 weeks
- Prince George's County8–16 weeks
- Baltimore County10–20 weeks
- Washington, D.C. (Filed Projects)30 business days