Montgomery County DPS is one of the busiest permit offices in the mid-Atlantic. Residential projects typically take 4 to 10 weeks; commercial work runs 6 to 14 weeks or more for tenant improvements. The single biggest variable in either case is the quality of your first submission.
Residential Permit Timelines by Project Type
- Additions and major alterations: 4–10 weeks for initial review
- Basement finishes and interior alterations: 4–8 weeks
- Decks, pools, and accessory structures: 4–8 weeks
- Trade permits (HVAC, electrical, plumbing): 3–6 weeks
- Small projects eligible for Residential Fast Track: generally 1–2 business days
Commercial Permit Timelines
Commercial tenant improvements typically run 6–14 weeks for initial review, and new commercial construction 10–20 weeks, depending on complexity and current DPS volume. Projects in areas with active Sector Plans face coordination with the Planning Department on top of DPS review, which extends the critical path. Spring and summer submission surges slow everything down. If you can file in winter, do.
Which Projects Qualify for Fast Track Review?
DPS runs two fast lanes. Residential Fast Track covers eligible small projects such as single-level decks and small sheds, and permits are generally issued in 1–2 business days. Commercial Fast Track covers small interior alterations in business and mercantile spaces, often with comments or a permit by the next business day. DPS also offers walk-through review for some residential and commercial scopes. Everything else goes through standard review, where clean scope definition, complete energy documentation and stamped drawings decide how many correction cycles you face.
Why Submissions Get Kicked Back
- Missing energy compliance documentation (ResCheck/COMcheck); Maryland enforces energy performance standards on most projects
- Unstamped drawings where an RA or PE seal is required
- Incomplete site plans or setback documentation
- Scope descriptions that don't match the drawings
- Outstanding code violations on the property requiring a Violation Removal Permit first
Rockville City vs. County: Which Jurisdiction Covers Your Property
Rockville and Gaithersburg are independent cities with their own permit offices and their own timelines. Properties inside city limits do not file with DPS at all. Bethesda, Silver Spring, Chevy Chase, Wheaton, and most of the county are DPS territory. In Takoma Park, DPS issues the building permit, but the city requires a municipality letter first. Filing with the wrong office wastes weeks, so confirm jurisdiction by address before preparing anything.
How to Check the Status of Your Application
DPS's ePlans portal shows review status, assigned reviewers, and comments in real time, and status updates arrive by email through the review cycle. If an application sits in one discipline's queue unusually long, a polite, specific follow-up referencing the application number is appropriate, and it's part of what a permit expediter does daily.
Get a Realistic Timeline for Your Project
PermitCare has worked Montgomery County DPS since 1999. We know which scopes fit Fast Track review and how to keep packages out of the correction cycle. Send us the address and scope for a realistic timeline.